Public Notice: Airport Work Scheduled This Summer

 

The Municipality of Blanc-Sablon is sharing a notice received about upcoming work to the airport this summer.

 

UPDATE FROM TRANSPORT CANADA July 15th, 2024

The works for the parking lot will be extended until August.

 

Notice of Works

 

Here are the phases as currently scheduled for the runway:

 

Phase 1: Half-width runway closure for approx. 2 weeks, 24m/75 ft. wide runway accessible during the day, runway closed at night (8:00 pm to 6:30 am), emergency helicopter evacuations and non-emergency evacuations postponed until after 6:30 am. The period currently defined for this phase is from 2024-07-01 to 2024-07-19.

 

Phase 2: Complete runway closure, runway not accessible day or night. The range currently defined for this phase is from 2024-07-20 to 2024-07-27.  Emergency and non-emergency evacuations will be carried out by helicopter.

 

Phase 3: Half-width runway closure for approximately 2 weeks, 24m/75 ft wide runway accessible during the day, runway closed at night (20:00 to 06:30), emergency evacuations by helicopter and non-emergency evacuations postponed until after 6:30 am.  The range currently defined for this phase is from 2024-07-28 to 2024-08-17.

 

 

1149 Dr. Camille Marcoux,
P.O. Box 400
Lourdes-de-Blanc-Sablon, QC
G0G 1W0

Tel. : 418 461-2707
Fax : 418 461-2529
information@mbsablon.com

Opening Hours
Frrom monday to Friday
8:30 to 12:00 and 13:00 to 16:30
CONTACT US
We look forward to hearing from you.

Questions?